Prince Albert City Council awarded the tender to Graham Construction LP in June of 2022, and on-site work started later in June of 2022. Site preparation occurred last year.
This project is funded in part by the Government of Canada and the Government of Saskatchewan.
Here's the latest update:
May 2024 Progress |
Contruction Notes to Follow. |
March 2024 Progress |
Building Construction Progress - March 2024 Arenas:
Lobby:
Aquatics:
|
January 2024 Progress |
The Aquatic and Arenas Recreation Project broke ground in July 2022, and progress on the project remains steady. The facility construction has surpassed the halfway mark and is scheduled for substantial project completion by the end of 2024. Thursday January 4th, 2024, Mayor Greg Dionne and Councillor Don Cody toured the facility with Graham Construction as the concrete slab for the north rink was poured. The new recreation facility includes a 51,500 square foot aquatics area featuring a 9-lane competitive pool, combined leisure, splash and wave pool, lazy river, whirlpool and two water slides. The twin arena area is 77,159 square feet and features 2 - NHL-sized rinks, larger player and referee dressing rooms and an expanded seating area. “The construction of a facility this size is a substantial undertaking,” said Mayor Greg Dionne. “You can see the level of precision that goes into a build like this when touring the facility.” Interesting arena ice slab facts:
Spectator Seating
Other interesting facts about the facility:
|
November 2023 Progress |
ArenasStructure/Exterior:
Interior:
LobbyInterior:
Aquatics:
Exterior:
Interior:
|
September 2023 Progress |
- Structural steel for north arena complete. - Precast Panels installed on north arena and access infill on south arena. - Metal Decking to north arena was completed and roofing began. - Exterior framing, boarding and insulation continued on east and north sides. Interior: - Mechanical and electrical rough-ins continued. Ductwork and plumbing continued in change rooms and south arena. - Forming for topping slab and risers continued north side. - Stairs were installed. - Ice Refrigeration equipment continued progress in refrigeration equipment room. - South arena ice surface preparation ongoing.
Structure/Exterior: - Skylight framing was installed.
Interior: - Masonry walls were completed in the concession/future retail spaces. - Mechanical roughins continued. - Elevator Hoist beam grouted in place.
- Roofing progress continued and is nearly complete. - Exterior framing, boarding, and insulation continued. - Glazing continued. Interior: - The change room area slabs were completed. - West Side of competition pool deck formed and poured. - Splash Pad area formed. - Pool splash pad accessory bases were installed and plumbed. - Wave pools walls forming and reinforcement began. - Masonry completed on 2nd floor in mechanical space. - Masonry began in basement and was mostly completed. - SFRM Fireproofing was completed. - Air handler installed on 2nd floor. - Mechanical and electrical roughins continued. |
August 2023 Progress |
Arenas: - Structural steel for north arena mostly complete. - Vapour barrier and insulation installation continued. - Mechanical and electrical rough-ins continued. Ductwork and plumbing continued in change rooms and south arena. - Ice Refrigeration equipment was placed and plumbing work began in mechanical spaces. - Masonry walls were mostly completed. - Remaining hollowcore was installed. Forming for topping slab and risers continued on north side.
Lobby: - Parapet and skylight framing was completed. - Glazing frames and glazing work continued. - Precast veneer panel install completed. - Steel stud soffit framing continued. - Mechanical above ceiling roughins began. - Slab preparation began for initial pour. - Above grade plumbing and sprinkler work began. - Stairs were delivered and installed. Aquatics: - Structural Steel continued. Most structure is in place with infill piece install in progress. - Exterior steel stud and boarding continued. - Aluminum framing and glazing progressed. - Precast veneer panel installation continued and is mostly complete. - Metal decking installed to roof and 2nd floor mechanical space. - Parapet framing is mostly complete except for north elevation. - Roofing install commenced on the south portion of Aquatics. - Below grade pool piping continued with encasement preparation. - Concrete Slab and housekeeping pads were poured for 2nd floor mechanical. - Masonry began on 2nd floor mechanical. - Underslab mechanical and electrical services in the change room area completed. - Slab preparation for change areas was completed. - Blue duct (buried) installation continued. - Pool filters were delivered to site and set in the basement.
- Utility Installation continued. - Backfilling to grade continued. - Formed and poured exterior entrance slabs and generator pad |
July 2023 Progress |
Arenas:
Lobby:
Aquatics:
|
June 2023 Progress |
The following work was completed in the month of June 2023: Arenas:
Lobby:
Aquatics:
|
May 2023 Progress |
The following work was completed in the month of April and May:
Drone footage of the site mid May 2023:
|
April 2023 Progress |
The following work was completed in the month of March and April:
Video: Drone footage of the site early April 2023:
|
March 2023 Progress |
The following work was completed in the month of February:
Video: Drone footage of the site end of February 2023:
|
February 2023 Progress |
Here are a few highlights of the construction progress made by the beginning of February 2023 on the Aquatics and Arenas Project:
Video: Drone footage of the site February 2023:
|
January 2023 Progress |
Here are a few highlights of the construction progress made during January 2023 on the Aquatics and Arenas Project:
Video: Drone footage of the site January 2023:
|
December 2022 Progress |
Construction on the Aquatics and Arenas Project is ongoing, and here are a few highlights of the progress made during November 2022:
|
November 2022 Progress |
The new Aquatics and Arenas Recreation centre is 10% into construction. Here are some interesting facts about how the construction is coming together:
|
October 2022 Progress |
Update for October 4, 2022: In this video, you will see the progress made on the new Recreation Centre:
Video: Drone footage of the site: October 4, 2022
|
September 2022 Progress |
Updates:
Video 1: Drone Footage of the site: September 13, 2022
Video 2: Inserting Drill Piles: September 13, 2022
|
August 2022 Progress |
Updates:
Drone Footage: August 16, 2022
Drone footage: August 4, 2022
|
July 2022 Progress |
Updates:
|
June 2022 Progress |
Tender awared to Graham Construction.
|