The following work was completed in the month of August:
Arenas:
- Structural steel for north arena mostly complete.
- Vapour barrier and insulation installation continued.
- Mechanical and electrical rough-ins continued. Ductwork and plumbing continued in change rooms and south arena.
- Ice Refrigeration equipment was placed and plumbing work began in mechanical spaces.
- Masonry walls were mostly completed.
- Remaining hollowcore was installed. Forming for topping slab and risers continued on north side.
Lobby:
- Parapet and skylight framing was completed.
- Glazing frames and glazing work continued.
- Precast veneer panel install completed.
- Steel stud soffit framing continued.
- Mechanical above ceiling roughins began.
- Slab preparation began for initial pour.
- Above grade plumbing and sprinkler work began.
- Stairs were delivered and installed.
Aquatics:
- Structural Steel continued. Most structure is in place with infill piece install in progress.
- Exterior steel stud and boarding continued.
- Aluminum framing and glazing progressed.
- Precast veneer panel installation continued and is mostly complete.
- Metal decking installed to roof and 2nd floor mechanical space.
- Parapet framing is mostly complete except for north elevation.
- Roofing install commenced on the south portion of Aquatics.
- Below grade pool piping continued with encasement preparation.
- Concrete Slab and housekeeping pads were poured for 2nd floor mechanical.
- Masonry began on 2nd floor mechanical.
- Underslab mechanical and electrical services in the change room area completed.
- Slab preparation for change areas was completed.
- Blue duct (buried) installation continued.
- Pool filters were delivered to site and set in the basement.
Exterior:
- Utility Installation continued.
- Backfilling to grade continued.
- Formed and poured exterior entrance slabs and generator pad